Case Studies - Examples Of Tools & Techniques

Welcome to the Case Studies Overview section of Bak2Basiks Ltd. Here, we proudly present an image gallery that showcases the global clients that we have worked with, while contracting & employed.  

 

The following case studies help to support the value added across varying sectors.  

 

The aim is not to overload with data, however should you require further information please request 

Case Studies

Examples Of Value Added

Mace Group 

  • 40 LH: 4mth Program Recovery £8 - £16M
  • 40 LH: 16 Week Program Recovery (Raised Floors)
  • LH 40: 2,900m2 Sto Render Ceiling Install Ontime 
  • 40 LH: Fire Stopping Managed / Delivered
  • HS2 Euston: 138 Outstanding Works Orders Cleared 
  • HS2 Euston: Sub Con Work Packs 18mth Delays recovered In 6 Weeks
  • THFC: Recovered 5mth Commissioning Program over Run,
  • THFC: Resolved Trade Issues & Cleared 338 Issue Back Log (Daily Control Room)
  • THFC: Reduced Commissioning Program Overrun By 7 Weeks
  • THFC: Coordinated Commissioning Of 8,488 Final Circuits - 619 CCTV's - Plus 26 Other Areas Of Multiple Testing

Aggreko

  • Ratified 3,500 SKU's (Pack Development)
  • Improved $148m Stock Accuracy  54% To 99%
  • Reduced Container Packing By 60%
  • Improved Ontime Delivery To 148 Global Sites 
  • Introduced Barcoding Control To All Stock 

TRU & N - Hub

  • HUB:  Delivered In House Project £10.1m 
  • HUB:  Resolved 43 key Issues De Risking £4.2m
  • HUB:  Supported 3 Blockades & Developed Control Rooms (De Risking £25m / Blockade) 121 Issues Resolved 10 Critical 
  • TRU :  Descoped 53% Survey Scope Valued At £1.8m
  • TRU; Managed £148m Opportunity Register Developing Focus Projects 

Sparrows

  • Resolved 128 Client Contract Issues (Control Room) 
  • Resolved & Removed £250k Platform Overspend
  • Reduced Offshore Labour Cost By £2.6m 
  • Reduced Re Work By 70% $380k
  • Improved EBITDA $1.85m
  • Reduced Crane Build Time From 42 wks - 34 Wks

Control Room Example 

The Example Shared Is Focusing On The Commissioning & Client Handover Of The THFC Stadium. 

 

Control Rooms / War Rooms have delivered some superb results on past projects, especially resolving complex process issues.  Bak2Basiks Ltd specialises in the development, facilitation &application of improvement Tools & Techniques.  "Keeping It Simple" works on every occasion.

 

Terms Of Reference Include: 

  • 30 Minutes Daily "Standing" Meetings
  • Involving The Correct People 
  • Utilising Reliable & Valid Data
  • Development of visual tools to interrogate & measure performance / recovery 
  • Development Of 7 Day "Lookaheads", Identifying Blockers & Micro Planning Improvements
  • Identifying / Resolving  Risk, Escalations & Support Requirements

Ready to Transform Your Business?

Contact Us Today!

Let us help you achieve your business goals. With specialsed services ranging from troubleshooting to team development, we are equipped to drive your organisation forward.

We need your consent to load the translations

We use a third-party service to translate the website content that may collect data about your activity. Please review the details in the privacy policy and accept the service to view the translations.